Switchgear Manufacturing

1. DESIGN & ENGINEERING PROCESS

1.1 New Order

After receiving an order, project file which includes Contract,technical specifications and Scope of supply etc. is given to Design & Engineering Manager for review and project planning.

Design & Engineering manager assigns one Electric Design engineer who is going to handle this project. Project file is also checked by Electric Design engineer.

1.2 Project Kick-Off

To Design & Orderhandling from Bid & Proposal :
Contract,technical specifications, Scope of supply and technical data sheet are handed over Electric design engineer.

Rate this blog entry:
20
Continue reading
3953 Hits

AutoTranslation

Web Traffic

12809
This WeekThis Week75
This MonthThis Month91
3.226.245.48

Random Post

1. DESIGN & ENGINEERING PROCESS 1.1 New Order After receiving an order, project file which includes Contract,technical specifications and Scope of supply etc. is given to Design & Enginee...
Rate this blog entry:
20
3953 hits

Most Popular

Cash is a medium of exchange for goods and services. Cash provides flexibility. Cash flow equals cash receipts minus cash payments over a given period of time. When you sell a product, you can...
Rate this blog entry:
24
4935 hits